Performing Arts Center: Difference between revisions
No edit summary |
No edit summary |
||
(11 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
==About== | ==About== | ||
After survey results showed a preference for a [[Performing Arts Center]], construction on one began in the [[2015-2016]] School year. Costing around 14 Million | After survey results showed a preference for a [[Performing Arts Center]], construction on one began in the [[2015-2016]] School year. Costing around 14 Million U.S. Dollars to construct, it has changed contracters two times and is currently underway to be finished by the end of the [[2017-2018]] school year, later than promised. | ||
The Performing Arts Center will be utilized by classes of the [[5000 building]] and potentially by other third party users. | The Performing Arts Center will be utilized by classes of the [[5000 building]] and potentially by other third party users. The building was financed via the same Prop P funds made available for the building of [[Sage Creek High School]] itself[https://www.carlsbadusd.k12.ca.us/pf4/cms2/view_page?d=x&group_id=1517645644742&vdid=i19a1quezz7]. | ||
The center was already being booked before even being completed due to the planned closure of the Carlsbad Community Cultural Arts Center. | |||
==Facilities== | |||
===[[6000 building]](PAC)=== | |||
*[[6001]] | |||
*[[6002]] | |||
==History== | |||
===Planning=== | |||
A number of project proposals appear to have been created for the PAC[https://web.archive.org/web/20170420035356/http://www.sillmanwright.com/current_perfarts.html][http://www.rachlinarchitects.com/m/work/project/sage-creek-performing-arts-center], but ultimately Rachlin Partners[http://www.rachlinarchitects.com/m/work/project/sage-creek-performing-arts-center] design was the one chosen. | |||
===Construction=== | ===Construction=== | ||
[[File:PACConstructionViaDrone2017december.jpg|thumb|left|The [[Performing Arts Center]] view from a drone in December 2017.]] | [[File:PACConstructionViaDrone2017december.jpg|thumb|left|The [[Performing Arts Center]] view from a drone in December 2017.]] | ||
Demolition of the stairways began as school was getting out in the [[2015-2016]] school year[https://web.archive.org/web/20180808064848/https://twitter.com/SCBobcats/status/614583647560036352]. | |||
The demolition would later remove part of the entry staircase, the handicap ramp, the [[Grass Hill]], and the wall next to the [[5000 building]]. | |||
===Ribbon Cutting=== | |||
On June 4th, [[2018]], the PAC opened to the public with a ribbon cutting held at 3:00pm. | |||
[[Category:Facilities]][[Category:6000 building]] |
Latest revision as of 20:01, 11 August 2018
About
After survey results showed a preference for a Performing Arts Center, construction on one began in the 2015-2016 School year. Costing around 14 Million U.S. Dollars to construct, it has changed contracters two times and is currently underway to be finished by the end of the 2017-2018 school year, later than promised.
The Performing Arts Center will be utilized by classes of the 5000 building and potentially by other third party users. The building was financed via the same Prop P funds made available for the building of Sage Creek High School itself[1].
The center was already being booked before even being completed due to the planned closure of the Carlsbad Community Cultural Arts Center.
Facilities
6000 building(PAC)
History
Planning
A number of project proposals appear to have been created for the PAC[2][3], but ultimately Rachlin Partners[4] design was the one chosen.
Construction
Demolition of the stairways began as school was getting out in the 2015-2016 school year[5].
The demolition would later remove part of the entry staircase, the handicap ramp, the Grass Hill, and the wall next to the 5000 building.
Ribbon Cutting
On June 4th, 2018, the PAC opened to the public with a ribbon cutting held at 3:00pm.